Anticipated Work for the Next Month
July 13, 2025 to August 14, 2026:
​​
Status of Work
-
Bridge coating
-
Slope paving (55%)
-
Interchange earth and drainage works ongoing
-
Colonel Talbot Road northbound lanes earth excavation, installation of clay fill, granulars, sewers and culverts, undergound electrical
-
Tempo Road earth excavation and granulars
-
Topsoil and seeding ongoing while weather permits
​​​​​
Current Lane Closures - Week of August 4th, 2026
​​
All interchange eastbound and westbound on and off ramps at Highway 401 and Colonel Talbot Road (Hwy 4) will be closed to all traffic
-
Tuesday, April 7th, 2026 at 07:00 until Friday, November 27th, 2026 at 23:59
Highway 401 eastbound and westbound driving lane (L2) closure from 1.5 km west of to 1.5 km east of Colonel Talbot Road
-
Monday, June 22nd, 2026 at 07:00 to Friday, November 6, 2026 at 23:59
Highway 4 (Colonel Talbot Road) northbound and southbound traffic will be reduced to a single lane in each direction from Orr Drive to Decker
-
Monday, June 8th, 2026 at 7 am to Monday, October 5th, 2026 at 7 am
Tempo Road will be closed to ALL traffic from Colonel Talbot Road to 300 m east of Colonel Talbot Road
-
Friday, June 19th, 2026 at 07:00 to Tuesday, September 8th, 2026 by 18:00
Highway 4 (Colonel Talbot Road) northbound and southbound traffic may be intermittently reduced to a single lane controlled by flagpersons from 1 km north to 1 km south of Highway 401
-
Tuesday, August 4th, 2026 to Friday, August 7th, 2026 from 07:00 to 18:00 daily
The following section provides general information related to construction and does not change.
​​​
SUMMARY OF CONSTRUCTION BY YEAR
​2024 Construction Season:
-
Construct median piers for new Highway 4 (Colonel Talbot Road) bridge
-
Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge
-
Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median
-
Reconstruct Highway 401 median storm sewer and sewer crossings
-
Construct western realignment half of Tempo Road
-
Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place
-
Install HML
​
2025 Construction Season:
-
Construct new Highway 4 (Colonel Talbot Road) bridge offline
-
Construct abutments with approaches and install new girders for new Highway 4 bridge
-
Construct the Tempo Road Realignment
-
Construct new Glanworth Drive bridge and deck structure
-
Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place
-
Widen northern portion of Highway 4
-
Remove existing Glanworth Drive bridge
​
2026 Construction Season:
-
Construct new Highway 4 bridge deck and structure
-
Complete widening and realignment of Highway 4 except surface course paving
-
Construct new interchange ramps and speed change lanes
-
Remove existing Highway 4 bridge
-
Construct southbound lanes of Colonel Talbot Road
-
Construct realignment of Burtwistle Lane
​
2027 Construction Season:
-
Complete surface course paving and construction of raised median on Highway 4
-
Complete surface course paving of interchange ramps
-
Construct aesthetic monuments at Highway 4 Underpass
-