Highway 401 and Highway 4 (Colonel Talbot Road) Interchange Reconfiguration
& Highway 4 (Colonel Talbot Road) and Glanworth Drive Bridge Replacements

Construction
The following sections will be updated weekly to reflect construction updates and traffic impacts.
​​​
Anticipated Work for the Next Month
September 22, 2025 to October 17, 2025:
​​
Glanworth Drive
-
Shouldering, guiderail, installation of signs
-
Pavement markings
​
Colonel Talbot Road North Portion
-
Pavement markings
-
Activation of temporary signals at tie-ins
-
Installation of permanent streetlighting at existing intersection
​
Colonel Talbot Road Structure
-
Form Deck
-
Clay Fill
​​
Littlewood Drive
-
Shouldering
​
Tempo
-
Topsoil and seeding
Hwy 401 Culvert Extensions
•Culvert 4, 5
​
Littlewood/Glanworth/Colonel Talbot Tie-Ins
-
Earth excavation
-
Granular B and A placement
-
Landscaping/restoration
-
Asphalt paving and shouldering
-
Pavement markings and permanent signs
​​​
Traffic Impacts for the Next Month
-
Daytime closure N-E Ramp at Colonel Talbot Road
-
Colonel Talbot Road from Highway 401 to 1 km north of Highway 401 intermittently reduced to a single lane controlled by flag persons
-
Hwy 401 driving lane eastbound and westbound for New Glanworth Structure overhead work, culvert extensions
-
Tempo Road between the IBEW Union Hall and Glanworth
​
Current Lane Closures - Week of October 20, 2025
​
NOTICE:
Tempo Road from the IBEW Union Hall to Glanworth Drive is closed to traffic:
July 29, 2025 until approximately November 14, 2025.
The S-W and W-N ramps (westbound on ramp and eastbound off ramp) are closed to traffic starting August 12th to November 28th.
​
Colonel Talbot Road northbound and southbound will intermittently reduced to a single lane controlled by flag persons between Littlewood Drive to Decker Drive
-
Monday, October 20, 2025 to Friday, October 24, 2025 from 7 am to 6 pm daily
Littlewood Drive from Colonel Talbot Road to Cook Road will intermittently be reduced to a single lane controlled by flag persons
-
Monday, October 20, 2025 to Friday, October 24, 2025 from 7 am to 6 pm daily
Glanworth Drive from Colonel Talbot Road to Wonderland Road will intermittently be reduced to a single lane controlled by flag persons
-
Monday, October 20, 2025 to Friday, October 24, 2025 from 7 am to 6 pm daily
Highway 401 eastbound and westbound driving lanes from 1.5 km east of Colonel Talbot Road 0.5 km east of Colonel Talbot Road
-
Sunday, October 19, 2025 at 10 am to Saturday, November 1, 2025 at 6 pm
UPCOMING CLOSURES:
Highway 401 full closure of eastbound and westbound lanes from Colonel Talbot Road to Highway 402
-
is closed to ALL traffic: Saturday, October 18, 2025 at 6 pm to Sunday, October 19, 2025 at 10 am
The westbound on ramps at Wonderland Road
-
are closed to ALL traffic: Saturday, October 18, 2025 at 6 pm to Sunday, October 19, 2025 at 10 am
The eastbound on ramp from southbound Colonel Talbot Road to Highway 401 (N-E Ramp)
-
is closed to traffic: Saturday, October 18, 2025 at 6 pm to Sunday, October 19, 2025 at 10 am
The eastbound on ramp from northbound Colonel Talbot Road to Highway 401 (S-E Ramp)
-
is closed to traffic: Saturday, October 18, 2025 at 6 pm to Saturday, November 1, 2025 at 6 pm
Highway 401 eastbound and westbound driving lanes from 1.5 km east of Colonel Talbot Road 0.5 km east of Colonel Talbot Road
-
Sunday, October 19, 2025 at 10 am to Saturday, November 1, 2025 at 6 pm
​
Detour Route for upcoming Full Closure
​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​
The following section provides general information related to construction and does not change.
​​​
SUMMARY OF CONSTRUCTION BY YEAR
​2024 Construction Season:
-
Construct median piers for new Highway 4 (Colonel Talbot Road) bridge
-
Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge
-
Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median
-
Reconstruct Highway 401 median storm sewer and sewer crossings
-
Construct western realignment half of Tempo Road
-
Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place
-
Install HML
​
2025 Construction Season:
-
Construct new Highway 4 (Colonel Talbot Road) bridge offline
-
Construct abutments with approaches and install new girders for new Highway 4 bridge
-
Construct the Tempo Road Realignment
-
Construct new Glanworth Drive bridge and deck structure
-
Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place
-
Widen northern portion of Highway 4
-
Remove existing Glanworth Drive bridge
​
2026 Construction Season:
-
Construct new Highway 4 bridge deck and structure
-
Complete widening and realignment of Highway 4 except surface course paving
-
Construct new interchange ramps and speed change lanes
-
Remove existing Highway 4 bridge
-
Construct southbound lanes of Colonel Talbot Road
-
Construct realignment of Burtwistle Lane
​
2027 Construction Season:
-
Complete surface course paving and construction of raised median on Highway 4
-
Complete surface course paving of interchange ramps
-
Construct aesthetic monuments at Highway 4 Underpass
-
Complete remaining portions of median tall wall barrier