The following sections will be updated weekly to reflect construction updates and traffic impacts.

​​​

Anticipated Work for the Next Month

September 22, 2025 to October 17, 2025:

​​

Glanworth Drive

  • Shouldering, guiderail, installation of signs

  • Pavement markings

​

Colonel Talbot Road North Portion

  • Pavement markings

  • Activation of temporary signals at tie-ins

  • Installation of permanent streetlighting at existing intersection

​

Colonel Talbot Road Structure

  • Form Deck

  • Clay Fill

​​

Littlewood Drive

  • Shouldering

​

Tempo

  • Topsoil and seeding

 

Hwy 401 Culvert Extensions

•Culvert 4, 5

​

Littlewood/Glanworth/Colonel Talbot Tie-Ins

  • Earth excavation

  • Granular B and A placement

  • Landscaping/restoration

  • Asphalt paving and shouldering

  • Pavement markings and permanent signs

​​​

Traffic Impacts for the Next Month

  • Daytime closure N-E Ramp at Colonel Talbot Road

  • Colonel Talbot Road from Highway 401 to 1 km north of Highway 401 intermittently reduced to a single lane controlled by flag persons

  • Hwy 401 driving lane eastbound and westbound for New Glanworth Structure overhead work, culvert extensions

  • Tempo Road between the IBEW Union Hall and Glanworth 

​

Current Lane Closures - Week of October 20, 2025

​

NOTICE:

Tempo Road from the IBEW Union Hall to Glanworth Drive is closed to traffic:

July 29, 2025 until approximately November 14, 2025.

The S-W and W-N ramps (westbound on ramp and eastbound off ramp) are closed to traffic starting August 12th to November 28th.

​

Colonel Talbot Road northbound and southbound will intermittently reduced to a single lane controlled by flag persons between Littlewood Drive to Decker Drive

  • Monday, October 20, 2025 to Friday, October 24, 2025 from 7 am to 6 pm daily

 

Littlewood Drive from Colonel Talbot Road to Cook Road will intermittently be reduced to a single lane controlled by flag persons

  • Monday, October 20, 2025 to Friday, October 24, 2025 from 7 am to 6 pm daily

 

Glanworth Drive from Colonel Talbot Road to Wonderland Road will intermittently be reduced to a single lane controlled by flag persons

  • Monday, October 20, 2025 to Friday, October 24, 2025 from 7 am to 6 pm daily

  

Highway 401 eastbound and westbound driving lanes from 1.5 km east of Colonel Talbot Road 0.5 km east of Colonel Talbot Road

  • Sunday, October 19, 2025 at 10 am to Saturday, November 1, 2025 at 6 pm

 

 

UPCOMING CLOSURES:

 

Highway 401 full closure of eastbound and westbound lanes from Colonel Talbot Road to Highway 402

  • is closed to ALL traffic: Saturday, October 18, 2025 at 6 pm to Sunday, October 19, 2025 at 10 am

 

The westbound on ramps at Wonderland Road

  • are closed to ALL traffic: Saturday, October 18, 2025 at 6 pm to Sunday, October 19, 2025 at 10 am

 

The eastbound on ramp from southbound Colonel Talbot Road to Highway 401 (N-E Ramp)

  • is closed to traffic: Saturday, October 18, 2025 at 6 pm to Sunday, October 19, 2025 at 10 am

 

The eastbound on ramp from northbound Colonel Talbot Road to Highway 401 (S-E Ramp)

  • is closed to traffic: Saturday, October 18, 2025 at 6 pm to Saturday, November 1, 2025 at 6 pm

 

Highway 401 eastbound and westbound driving lanes from 1.5 km east of Colonel Talbot Road 0.5 km east of Colonel Talbot Road

  • Sunday, October 19, 2025 at 10 am to Saturday, November 1, 2025 at 6 pm

​

Detour Route for upcoming Full Closure

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

The following section provides general information related to construction and does not change.

​​​

SUMMARY OF CONSTRUCTION BY YEAR

​2024 Construction Season:

  • Construct median piers for new Highway 4 (Colonel Talbot Road) bridge

  • Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge

  • Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median

  • Reconstruct Highway 401 median storm sewer and sewer crossings

  • Construct western realignment half of Tempo Road

  • Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place

  • Install HML

​

2025 Construction Season:

  • Construct new Highway 4 (Colonel Talbot Road) bridge offline

  • Construct abutments with approaches and install new girders for new Highway 4 bridge

  • Construct the Tempo Road Realignment

  • Construct new Glanworth Drive bridge and deck structure

  • Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place

  • Widen northern portion of Highway 4

  • Remove existing Glanworth Drive bridge

​

2026 Construction Season:

  • Construct new Highway 4 bridge deck and structure

  • Complete widening and realignment of Highway 4 except surface course paving

  • Construct new interchange ramps and speed change lanes

  • Remove existing Highway 4 bridge

  • Construct southbound lanes of Colonel Talbot Road

  • Construct realignment of Burtwistle Lane

​

2027 Construction Season:

  • Complete surface course paving and construction of raised median on Highway 4

  • Complete surface course paving of interchange ramps

  • Construct aesthetic monuments at Highway 4 Underpass

  • Complete remaining portions of median tall wall barrier