Construction

The following sections will be updated weekly to reflect construction updates and traffic impacts.

​​

Anticipated Work for the Next Month

August 18, 2025 to September 12, 2025:

​

Glanworth Drive

  • Asphalt paving and shouldering

  • Pavement markings and signs, guiderail

 

Glanworth Drive Structure

  • Waterproofing and Paving

 

Colonel Talbot Road North Portion

  • Median Earth Excavation, Granular B, A

  • Underground electrical and traffic

  • Asphalt paving

 

Colonel Talbot Road Structure

  • Form Deck

  • Clay Fill


Littlewood Drive

  • Shouldering

  • Tempo

  • Asphalt paving

  • Topsoil and seeding

 

Hwy 401 Culvert Extensions

  • Culvert 2 week of July 28th

 

Littlewood/Glanworth/Colonel Talbot Tie-Ins

  • Mid-September

​​​

Traffic Impacts for the Next Month

  • Full Closure of W-N and S-W  Ramp closures at Colonel Talbot Road

  • Glanworth Drive Northbound and Southbound from Wonderland to Colonel Talbot intermittently reduced to a single lane controlled by flag persons

  • Littlewood Drive from Colonel Talbot Road to 500 m west of Colonel Talbot intermittently reduced to a single lane controlled by flag persons

  • Colonel Talbot Road from Highway 401 to 1 km north of Highway 401 intermittently reduced to a single lane controlled by flag persons

  • Hwy 401 driving lane eastbound and westbound for New Glanworth Structure overhead work, culvert extensions

  • Tempo Road between the IBEW Union Hall and Glanworth 

  • Nightly closures eastbound and westbound Highway 401 for girder erection

​

Current Lane Closures - Week of August 25, 2025

​​​​​​​​

NOTICE:

Tempo Road from the IBEW Union Hall to Glanworth Drive is closed to traffic:

July 29, 2025 until approximately September 15, 2025.

The S-W and W-N ramps (westbound on ramp and eastbound off ramp) are closed to traffic starting August 12th to November 28th.

​

​​Colonel Talbot Road northbound and southbound will intermittently reduced to a single lane controlled by flag persons between Littlewood Drive to Decker Drive

  • Monday, August 25, 2025 to Friday, August 29, 2025 from 7 am to 6 pm daily

​​

Glanworth Drive from Highway 401 to Wonderland Road will intermittently reduced to a single lane controlled by flag persons 

  • Monday, August 25, 2025 to Friday, August 29, 2025 from 7 am to 6 pm daily

​​

Littlewood Drive from Colonel Talbot Road to 500 m west of Colonel Talbot Road will intermittently be reduced to a single lane controlled by flag persons

  • Monday, August 25, 2025 to Friday, August 29, 2025 from 7 am to 6 pm daily

​​

Tempo Road from the IBEW Union Hall (300 m east of Colonel Talbot Road) to Glanworth Drive

  • is closed to traffic: Tuesday, July 29, 2025 at 7 am to Monday, September 15, 2025 at 6 pm

​​​

The westbound on ramp from Colonel Talbot to Highway 401 westbound (S-W Ramp) will be closed for construction and access

  • Tuesday, August 12, 2025 at 6 am to Friday, November 28, 2025 at 6 pm

​

The eastbound off ramp from Highway 401 to Colonel Talbot Road Northbound (W-N) will be closed for construction and access

  • Tuesday, August 12, 2025 at 6 am to Friday, November 28, 2025 at 6 pm​​​

​

​​Highway 401 eastbound driving lane from 1.5 km west of Colonel Talbot Road Underpass to 1.0 km west of Colonel Talbot Road Underpass will be closed for construction

  • Monday, August 25, 2025 at 6 am to Friday, August 29, 2025 at 11 am

 

Highway 401 eastbound and westbound high speed lanes from 300 m west of and to 300 m east of Colonel Talbot Road Underpass

  • Monday, August 25, 2025 at 6 am to Friday, August 29, 2025 at 11 am

​​

​​​​​​​​​​​​​​​The following section provides general information related to construction and does not change.

​​​

SUMMARY OF CONSTRUCTION BY YEAR

​2024 Construction Season:

  • Construct median piers for new Highway 4 (Colonel Talbot Road) bridge

  • Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge

  • Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median

  • Reconstruct Highway 401 median storm sewer and sewer crossings

  • Construct western realignment half of Tempo Road

  • Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place

  • Install HML

​

2025 Construction Season:

  • Construct new Highway 4 (Colonel Talbot Road) bridge offline

  • Construct abutments with approaches and install new girders for new Highway 4 bridge

  • Construct the Tempo Road Realignment

  • Construct new Glanworth Drive bridge and deck structure

  • Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place

  • Widen northern portion of Highway 4

  • Remove existing Glanworth Drive bridge

​

2026 Construction Season:

  • Construct new Highway 4 bridge deck and structure

  • Complete widening and realignment of Highway 4 except surface course paving

  • Construct new interchange ramps and speed change lanes

  • Remove existing Highway 4 bridge

  • Construct southbound lanes of Colonel Talbot Road

  • Construct realignment of Burtwistle Lane

​

2027 Construction Season:

  • Complete surface course paving and construction of raised median on Highway 4

  • Complete surface course paving of interchange ramps

  • Construct aesthetic monuments at Highway 4 Underpass

  • Complete remaining portions of median tall wall barrier