The following sections will be updated weekly to reflect construction updates and traffic impacts.

Anticipated Work for the Next Month

June 15, 2025 to July 10, 2026:

Status of Work

  • Complete bridge coating

  • Continue with slope paving

  • Continue Interchange earth and drainage works

  • Placement of granulars

  • Existing electrical removals and new installations

Current Lane Closures - Week of June 22nd,  2026

All interchange eastbound and westbound on and off ramps at Highway 401 and Colonel Talbot Road (Hwy 4) will be closed to all traffic

  • Tuesday, April 7th, 2026 at 07:00 until Friday, November 27th, 2026 at 23:59

 

Highway 401 eastbound and westbound driving lane (L2) closure from 1.5 km west of to 1.5 km east of Colonel Talbot Road

  • Monday, June 22nd, 2026 at 07:00 to Friday, November 6, 2026 at 23:59

 

Highway 4 (Colonel Talbot Road) northbound and southbound traffic will be reduced to a single lane in each direction from Orr Drive to Decker

  • Monday, June 8th, 2026 at 7 am to Monday, October 5th, 2026 at 7 am

 

Tempo Road will be closed to ALL traffic from Colonel Talbot Road to 300 m east of Colonel Talbot Road

  • Friday, June 19th, 2026 at 07:00 to Tuesday, August 4th, 2026 by 18:00

 

Highway 4 (Colonel Talbot Road) northbound and southbound traffic may be intermittently reduced to a single lane controlled by flagpersons from 1 km north to 1 km south of Highway 401

  • Monday, June 22ND, 2026 to Friday, June 26th, 2026 from 07:00 to 18:00 daily

 

The following section provides general information related to construction and does not change.

SUMMARY OF CONSTRUCTION BY YEAR

​2024 Construction Season:

  • Construct median piers for new Highway 4 (Colonel Talbot Road) bridge

  • Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge

  • Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median

  • Reconstruct Highway 401 median storm sewer and sewer crossings

  • Construct western realignment half of Tempo Road

  • Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place

  • Install HML

2025 Construction Season:

  • Construct new Highway 4 (Colonel Talbot Road) bridge offline

  • Construct abutments with approaches and install new girders for new Highway 4 bridge

  • Construct the Tempo Road Realignment

  • Construct new Glanworth Drive bridge and deck structure

  • Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place

  • Widen northern portion of Highway 4

  • Remove existing Glanworth Drive bridge

2026 Construction Season:

  • Construct new Highway 4 bridge deck and structure

  • Complete widening and realignment of Highway 4 except surface course paving

  • Construct new interchange ramps and speed change lanes

  • Remove existing Highway 4 bridge

  • Construct southbound lanes of Colonel Talbot Road

  • Construct realignment of Burtwistle Lane

2027 Construction Season:

  • Complete surface course paving and construction of raised median on Highway 4

  • Complete surface course paving of interchange ramps

  • Construct aesthetic monuments at Highway 4 Underpass

  • Complete remaining portions of median tall wall barrier