The following sections will be updated weekly to reflect construction updates and traffic impacts.

​​

Anticipated Work for the Next Month

June 23, 2025 to July 18, 2025:

  • Glanworth Drive South

    • Place Granular B and A

    • Backfill Abutments

    • Curbs

    • Fine grading

​​

  • Glanworth Drive North

    • Clay filling

    • Cut road to grade

    • Granular B placement

    • Topsoil

​​

  • New Glanworth​​​​​​​ Structure

    • Backfill abutments​

​​

  • Colonel Talbot Road North Portion

    • Switch traffic to the west side

    • ditching, removals

    • cutting and filling

    • electrical for intersection

​​​

  • Littlewood Drive

    • Cut to grade

    • Place Granular B and A

​​​

Traffic Impacts for the Next Month

​

  • Intermittent on and off ramps closures at Colonel Talbot Road

  • Highway 401 eastbound high speed lane from 1.5 km west to 1.5 km east of Colonel Talbot Road

  • Glanworth Drive Northbound and Southbound from Wonderland to Colonel Talbot intermittently reduced to a single lane controlled by flag persons

  • Littlewood Drive from Colonel Talbot Road to 500 m west of Colonel Talbot intermittently reduced to a single lane controlled by flag persons

  • Colonel Talbot Road from Littlewood Drive to Decker Drive intermittently reduced to a single lane controlled by flag persons

​​

Current Lane Closures - Week of July 14, 2025

​​​​​​​

​​Colonel Talbot Road northbound and southbound will intermittently reduced to a single lane controlled by flag persons between Littlewood Drive to Decker Drive

  • Monday, July 14, 2025 to Friday, July 18, 2025 from 7 am to 6 pm daily

​

Glanworth Drive from Highway 401 to Wonderland Road will intermittently reduced to a single lane controlled by flag persons 

  • Monday, July 14, 2025 to Friday, July 18, 2025 from 7 am to 6 pm daily

​

Littlewood Drive from Colonel Talbot Road to 500 m west of Colonel Talbot Road will intermittently be reduced to a single lane controlled by flag persons

  • Monday, July 14, 2025 to Friday, July 18, 2025 from 7 am to 6 pm daily

​​​

The westbound on ramp from Colonel Talbot to Highway 401 westbound (S-W Ramps) will be closed for construction and access

  • Monday to Friday, July 14 to 18, 2025 from 6 am to 6 pm

​

Highway 401 eastbound and westbound driving lane from Colonel Talbot Road Underpass to 700 m east of Colonel Talbot Road Underpass will be closed for construction

  • Monday, July 14, 2025 at 6 am to Friday, July 18, 2025 at 11 am

​

NOTICE:

The eastbound and wesrbound high speed lane from500 m west of Colonel Talbot Road to 1.5 km east of Colonel Talbot Road will be closed to traffic starting on Monday, July 21, 2025 for approximately 2 weeks

​​

​​​​​​​​​​​The following section provides general information related to construction and does not change.

​​

SUMMARY OF CONSTRUCTION BY YEAR

​2024 Construction Season:

  • Construct median piers for new Highway 4 (Colonel Talbot Road) bridge

  • Construct median piers abutments with approaches and install new girders for new Glanworth Drive bridge

  • Construct High Mast Lighting (HML) and overhead sign (OHS) footings along Highway 401 median

  • Reconstruct Highway 401 median storm sewer and sewer crossings

  • Construct western realignment half of Tempo Road

  • Commence realignment of Glanworth Drive and Littlewood Drive and construction of Littlewood Place

  • Install HML

​

2025 Construction Season:

  • Construct new Highway 4 (Colonel Talbot Road) bridge offline

  • Construct abutments with approaches and install new girders for new Highway 4 bridge

  • Construct the Tempo Road Realignment

  • Construct new Glanworth Drive bridge and deck structure

  • Complete construction of Littlewood Drive and Glanworth Drive realignments, Littlewood Drive and Littlewood Place

  • Widen northern portion of Highway 4

  • Remove existing Glanworth Drive bridge

​

2026 Construction Season:

  • Construct new Highway 4 bridge deck and structure

  • Complete widening and realignment of Highway 4 except surface course paving

  • Construct new interchange ramps and speed change lanes

  • Remove existing Highway 4 bridge

  • Construct southbound lanes of Colonel Talbot Road

  • Construct realignment of Burtwistle Lane

​

2027 Construction Season:

  • Complete surface course paving and construction of raised median on Highway 4

  • Complete surface course paving of interchange ramps

  • Construct aesthetic monuments at Highway 4 Underpass

  • Complete remaining portions of median tall wall barrier

© 2023 Dillon Consulting Limited.

GIP_Logo_white.png
ON_REV_LOGO_RGB.png
image.png
bottom of page